Workflow phases can be defined as part of the overall process description. Phases are found under Resources as outlined below:

Phases in simulation
Phases are shown in simulation in the DCR Simulation screen in the upper left corner.
The actual phase is calculated as:
- If any pending (and included) activities associated with a phase – the minimum phase
- If no pending activities- the largest phase associated with an executed event (and included)
- If anything is enabled – take the minimum phase of the enabled activities
- If nothing is is enabled – take the maximum phase of any executed activity
- If no pending or executed or enabled activities – the minimum phase defined in the graph – if any